Background
Before a new-build ship can be delivered to its owner, its engine must be proven to meet specifications. The proving process is a sequence of tests at progressively integrated levels:
- Shop test at the engine manufacturer’s factory: engine alone on dynamometer
- Dock trial in the shipyard: engine installed in ship, ship moored
- Sea trial: engine operating with ship in actual seaway
Each step verifies specific aspects of engine and integrated ship performance. Class society representatives witness key milestones; the engine and ship cannot be delivered until tests are completed satisfactorily.
This article covers the three trial phases, the principal measurements, and the documentation required for class approval and ship delivery.
Shop test
Test environment
Shop tests are performed at the engine manufacturer’s factory:
- Test bed: dedicated infrastructure for engine operation
- Dynamometer: water brake or motor-generator absorbing engine power
- Standard fuel: reference fuel for SFOC determination
- Standard ambient: air conditions controlled or corrected
Test points
Standard test points (per ISO 3046):
- 25%, 50%, 75%, 85% (CSR), 100% (MCR), 110% (overload) of rated power
At each point, the engine runs for a minimum time (typically 1 hour at the lower points, 6+ hours at MCR) to reach steady state. Measurements are then taken.
Measurements
At each test point:
- Power and speed via torque sensor and tachometer
- Fuel consumption via calibrated flow meter
- Cylinder pressures at each cylinder (all 720°CA capture)
- Exhaust temperatures at each cylinder
- Turbocharger speed, inlet/outlet temperatures, pressures
- Cooling water temperatures and flow rates
- Lubricating oil temperature, pressure, flow
- Charge air pressure, temperature, mass flow
- Ambient conditions: air temperature, pressure, humidity
SFOC determination
SFOC at each test point is calculated:
SFOC = m_fuel / P_brake × 3600 / 1000
ISO-corrected to standard reference conditions (25°C, 1 bar, 30% RH, fuel LCV 42,700 kJ/kg).
NOx measurement
NOx emission is measured via continuous emission monitoring (CEM):
- Sample line from exhaust manifold
- NOx analyser (chemiluminescence)
- ISO 8178-1 procedure
- Emission profile across load points
- Cycle-weighted average for certification
NOx must meet Tier II limit (or Tier III if the engine is Tier III certified).
Documentation
Shop test results documented in:
- Engine performance test report
- NOx test report (basis for EIAPP certificate)
- Cylinder pressure data per cylinder
- Anomaly reports
- Class society witness reports
These documents accompany the engine to the shipyard.
Dock trial
Purpose
Dock trial verifies that the engine works correctly in its installed configuration, integrated with ship systems, before going to sea.
Test setup
The ship is moored at the shipyard quay, fully equipped except awaiting sea trial. The engine is connected to:
- Ship’s fuel system
- Ship’s cooling water (or shore-side cooling for limited duration)
- Ship’s electrical system
- Ship’s lubricating oil system
- Ship’s bridge controls
Tests performed
Dock trial typically includes:
- Engine starting: from cold, with bridge command
- Idle running: prolonged idle to verify stability
- Reversing: ahead-astern transitions
- Variable speed: ramp from idle to rated
- Auxiliary system tests: lubricating oil pumps, cooling water pumps, fuel pumps
- Telegraph and bridge controls: command transmission and acknowledgement
- Alarm and shutdown: simulated faults trigger correct responses
- Cylinder lubricator: feed rate verification
- Air cooler operation: with ship’s seawater
- Indicator measurements: at attainable load points (limited by mooring)
Limitations
Dock trial cannot test:
- Full load operation (mooring lines and ship structure cannot absorb full power)
- Manoeuvring at speed
- Sea-state response
These wait for sea trial.
Duration
Dock trial typically takes 2-5 days, including any troubleshooting and recommissioning of items revealed during testing.
Sea trial
Purpose
Sea trial verifies engine performance and ship operation in actual seaway. The trial is the final acceptance test before ship delivery to the owner.
Test setup
The ship sails from the shipyard with:
- Owner’s representatives aboard
- Class society representatives aboard
- Yard test engineers and crew
- Manufacturer service engineers
- Test instrumentation
The trial is typically 2-7 days at sea, depending on test scope.
Standard test program
A typical sea trial program:
Day 1: Light operation
- Departure from yard
- Stable cruise at moderate load (50-70%)
- Initial system checks
- Fuel consumption baseline
Day 2: Power and speed
- Speed-power curve (15, 20, 25, 30 minutes at increasing speeds)
- Bollard pull verification (if applicable)
- Maximum speed determination
- Fuel consumption at each speed
Day 3: Performance verification
- Continuous service rating run (4-8 hours at CSR)
- SFOC determination at multiple loads
- Cylinder pressure measurements
- Exhaust temperature mapping
- Turbocharger performance
- ISO correction calculations
Day 4: Manoeuvring
- Steering trials
- Crash stop trials
- Astern trials
- Emergency stop trials
- Pilot ladder operations
Day 5: Emission verification
- NOx measurement at multiple loads
- Smoke level verification
- Emission compliance documentation
Days 6-7: Misc
- Auxiliary system performance
- Fuel switching tests (if multi-fuel)
- Sister ship comparison (if applicable)
- Final adjustments and rerun of any failed items
Specific tests
Speed-power test
Ship runs at various speeds; engine power and ship speed measured. Comparison to design predicts confirms hull performance.
Crash stop test
Ship at full speed; emergency astern command issued. Stopping distance and time measured. Verifies emergency response capability.
NOx test
Continuous emission monitoring during specific load points. Cycle-weighted NOx calculated and compared to certification.
Cylinder balance verification
PMI data collected at multiple operating points. Cylinder-to-cylinder variation measured. Adjustments made if needed.
Trials in different conditions
Sea trial may include:
- Calm sea conditions (baseline performance)
- Sea state 4-5 (operational seakeeping)
- Various headings (effect of wave direction)
- Various propulsion modes (if applicable)
Documentation
Sea trial results documented in:
- Sea trial report (full performance data)
- ISO-corrected SFOC curve
- Cylinder pressure baseline records
- Emission test report
- Anomaly log
- Class society witness statements
- Owner acceptance
Independent verification
Class society survey
Class society representatives:
- Witness shop test at engine factory
- Witness key dock trial tests
- Witness key sea trial tests
- Approve test reports
- Issue certificates
Owner inspection
Owner’s representatives accompany the test process:
- Verify specifications met
- Identify any commissioning items
- Record final condition
- Authorise delivery
Sister ship comparison
For ships in series, sea trial results are compared to sister ships:
- Identifies systematic issues
- Confirms expected performance reproducibility
- Supports optimization across the series
Acceptance and delivery
Acceptance criteria
The ship/engine is accepted if:
- All measured parameters within specification
- All ISO-corrected SFOC values within specification
- NOx emissions meet certification levels
- All safety systems function correctly
- Class society approval received
- Owner satisfaction confirmed
Delivery documents
Documents accompany delivery:
- Engine performance test reports
- EIAPP certificate (NOx compliance)
- Class society certificates
- Operating and maintenance manuals
- Spare parts inventory
- Ship’s classification documents
Post-delivery monitoring
After delivery, the engine undergoes initial service period (typically 6-12 months) with:
- Manufacturer service support
- Detailed performance monitoring
- Resolution of any commissioning issues
- Establishment of in-service baselines
This period validates the trial results and establishes the engine’s true operational baseline.
Related Calculators
- Sea Trial SFOC Verification Calculator
- Speed-Power Curve Calculator
- Crash Stop Distance Calculator
- NOx Cycle Weighted Average Calculator
- ISO Correction Factor Calculator
See also
- Engine Performance Monitoring (PMI) on Marine Engines
- Specific Fuel Oil Consumption Curves on Marine Engines
- Tier III Compliant Two-Stroke Engines
- Two-Stroke Marine Diesel Engine Fundamentals
References
- ISO 3046-1:2002. Reciprocating internal combustion engines: Performance.
- ISO 8178-1:2017. Reciprocating internal combustion engines — Exhaust emission measurement.
- IMO. (2008). NOx Technical Code 2008.
- MAN Energy Solutions. (2023). Engine Sea Trial Procedures Manual. MAN Energy Solutions.
- Lloyd’s Register. (2023). Sea Trials and Performance Tests Guide.